Korekcije cena i pomeranje rokova: Šta skrivaju aneksi ugovora za najveće infrastrukturne poslove u Srbiji?

I dok za Moravski koridor nadležno Ministarstvo građevinarstva nije objavilo u svojim informacijama o radu da je sklopljen i jedan aneks ugovora o izgradnji, za ostale projekte nalik tome, ti aneksi uglavnom postoje. I to u velikom broju.

Korekcije cena i pomeranje rokova: Šta skrivaju aneksi ugovora za najveće infrastrukturne poslove u Srbiji?

TL;DR

  • Many construction projects in Serbia, unlike the Morava Corridor, have numerous contract annexes.
  • These annexes often lead to increased costs and extended completion deadlines.
  • The Preljina-Požega highway experienced eight amendments, increasing its cost from $523.53 million to €633 million.
  • The Belgrade bypass (sector B) had 13 annexes, raising its initial cost of €207 million by nearly €174 million.
  • The Sremska Rača-Kuzmin and Požega-Kotroman sections of the Belgrade-Sarajevo road saw their price increase from €250 million to €408.5 million through one of nine annexes.
  • The Ruma-Šabac-Loznica road's cost escalated from €467.5 million to €1.04 billion with nine amendments.
  • The Belgrade-Novi Sad-Zrenjanin road's estimated value grew from €600 million to €1.59 billion.
  • The modernization of the Horgoš border crossing also saw eight annexes, mostly for price increases or deadline extensions.
  • The pattern of increased costs and delayed timelines is consistent across various projects and contractors.